- Boston Towers – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete
- Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete
- Spalding Towers – Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete
- Roxby Close – Laterals and Risers – 100% mechanical complete – Sprinklers – 100% complete. Wiring ongoing.
- Ferriby Towers – Laterals and Risers – 100% mechanical complete – , sprinklers and wiring ongoing
- Grantham Towers- Laterals – 100% completed. Risers – installed but not welded/lagged. – Sprinklers and wiring to install
- All Shakespeare buildings – Laterals – 100% mechanical complete, risers -80% complete, sprinklers and wiring to install
- Appleton Court – Laterals and Risers – 100% mechanical complete – wiring and sprinklers to install
- Appleton Close – Laterals and Risers – 100% mechanical complete – wiring and sprinklers to install
- Appleton Square – Laterals – 50% mechanical complete – risers,sprinklers and wiring to install.
- Saville Green – Laterals – 100% mechanical complete – risers,sprinklers or wiring to install
- Beckett Street – All works outstanding
- Cromwell Heights- All works outstanding
- Granville Road – All works outstanding
- Lincoln Towers – Laterals and Risers – 100% complete. Sprinklers 30% complete.tall. Electrical works outstanding
- Lindsey Mount – Laterals 100% completed – All other works outstanding
- Marston Mount – Laterals – 20% completed. Welding completed on 1st floor, Sprinklers 20% completed. All other works outstanding
- Torre Gardens – All works outstanding
- Torre Green – All works outstanding