Multi Storey Flats- Progress update

  • Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete
  • Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete
  • Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete
  • Roxby Close – Laterals  and Risers – 100% mechanical complete – Sprinklers – 100% complete. Wiring ongoing.
  • Ferriby Towers – Laterals and Risers  – 100% mechanical complete –Sprinklers – 100% complete – Wiring 100% complete
  • Grantham Towers- Laterals and Risers – 100% mechanical complete – Sprinklers 100% complete – wiring 100% complete
  • All Shakespeare buildings – Laterals  – 100% mechanical complete, risers -80% complete, sprinklers and wiring to install
  • Appleton Court – Laterals and Risers –  100% mechanical  complete – wiring and sprinklers to install
  • Appleton Close –  Laterals and Risers  – 100% mechanical complete – wiring and sprinklers to install
  • Appleton Square – Laterals and Risers – 100% mechanical complete – wiring and sprinklers to install
  • Saville Green – Laterals and Risers – 100% mechanical to complete – wiring and sprinklers to install
  • Beckett Street – All works outstanding
  • Cromwell Heights- Blocks 62-121 and 122-182 100% – mechanical complete – sprinkler riser 100% – wiring and sprinkler laterals to complete
  • Granville Road – All works outstanding
  • Lincoln Towers –  Laterals and Risers – 100% complete.  Sprinklers 100% complete.tall. Electrical works outstanding
  • Lindsey Mount –  Laterals and Risers – 100% complete – Sprinklers 100% complete – All electrical works outstanding
  • Marston Mount – Laterals – 80% completed. Welding completed on 1st floor, Sprinklers 100% completed. All other works outstanding
  • Torre Gardens – All works outstanding. Works are due to commence 07.01.2019