LATEST UPDATES

Multi Storey Flats- Progress update

  • Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete
  • Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete
  • Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete
  • Roxby Close – Laterals  and Risers – 100% mechanical complete – Sprinklers – 100% complete. Wiring ongoing.
  • Ferriby Towers – Laterals and Risers  – 100% mechanical complete –Sprinklers – 100% complete – Wiring 100% complete
  • Grantham Towers- Laterals and Risers – 100% mechanical complete – Sprinklers 100% complete – wiring 100% complete
  • All Shakespeare buildings – Laterals  – 100% mechanical complete, risers -80% complete, sprinklers and wiring to install
  • Appleton Court – Laterals and Risers –  100% mechanical  complete – 100% risers-wiring to complete
  • Appleton Close –  Laterals and Risers  – 100% mechanical complete – 100% risers-wiring to complete
  • Appleton Square – Laterals and Risers – 100% mechanical complete – 100% risers-wiring to complete
  • Saville Green – Laterals and Risers – 100% mechanical complete – 100% risers-wiring to complete
  • Beckett Street – Laterals and risers -100% mechanical complete – wiring to complete
  • Cromwell Heights- Laterals and risers – 100% mechanical complete – wiring 100% – sprinklers 100%
  • Granville Road – Laterals and risers 50% – wiring to complete
  • Lincoln Towers –  Laterals and Risers – 100% complete.  Sprinklers 100% complete – wiring 100%
  • Lindsey Mount –  Laterals and Risers – 100% complete – Sprinklers 100% complete – wiring 100%
  • Marston Mount – Laterals and risers – 100% complete – sprinklers 100% complete – wiring 100%
  • Torre Gardens – Laterals and risers – 100% complete – sprinklers and wiring to complete