Update on Road Disruption

As the Leeds PIPES network continues to progress, the vast majority of the district heating pipe installation is now complete. As a result, there is currently no traffic management in place in relation to the Leeds PIPES network.

Cross Green Energy Centre Progress

We are delighted to announce that the external structure at Cross Green has now been completely finished within the predicted timescale. All the major pieces of equipment have been delivered and are in the energy centre and Veolia have started the fit out of the steam room where the pipes will connect to the energy …

Read more

Multi Storey Flats- Progress update

Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete Roxby Close – Laterals  and Risers – 100% mechanical …

Read more

The Chimney Arrives at Saxton Gardens

We’re pleased to report that the progress continues on the Leeds PIPES project and the striking, orange chimney has arrived and been installed at the Saxton Gardens energy centre site. The chimney is 20m high, 2.9m in diameter and comprises 5 internal flues which are surrounded by an outer casing known as the windshield.  The …

Read more

Multi Storey Flats- Progress update

Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete Roxby Close – Laterals  and Risers – 100% mechanical …

Read more

Pre-Installation Surveys

We are now starting to complete our pre-installation surveys in readiness for connecting the properties to the new district heating system, which will commence in 2019. All tenants will receive a telephone call in order to book an appointment for a member of the Tenant Liaison team to attend and complete the pre-installation survey. During …

Read more

Multi Storey Flats- Progress update

Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete Roxby Close – Laterals  and Risers – 100% mechanical …

Read more

Pre-Installation Surveys

We are now starting to complete our pre-installation surveys in readiness for connecting the properties to the new district heating system, which will commence in 2019. All tenants will receive a telephone call in order to book an appointment for a member of the Tenant Liaison team to attend and complete the pre-installation survey. During …

Read more