Works on Clarence Road

 

As part of the ongoing works to expand district heating across Leeds, our team will be commencing works on Clarence Road on Monday 4th August.

These works will entail trial holes taking place Monday 4th August at 7.30 am, until main works commence on Monday 11th August at 7.30 am until Wednesday 19th November at 16:00 pm.

Works will take place from 7.30 am – 18.00 pm, Monday – Friday, with the possibility of occasional evening or weekend work and will also involve road excavations and the implementation of 2-, 3-, or 4-way temporary traffic lights throughout the sections of work.

No road diversions will be put in place due to no road closures. However, routes for temporary traffic lights will be displayed below.

We will strive to keep any disruption and noise to a minimum as we connect more of Leeds City Centre to reliable, affordable, low carbon, heating and hot water.

Please see images below. 

Section 1 – Clarence Road, 3-Way Lights 

Start Date: 11th August 2025

End Date: 10th September 2025

 

Section 2 – Clarence Road, 4-Way Lights 

Start Date: 28th August 2025

End Date: 10th September 2025

 

Section 3a & 3b- Clarence Road, 3-Way Lights

Start Date: 11th September 2025

End Date: 30th September 2025

Section 3a                                                                                              Section 3b

       

 

 

Section 4 – Clarence Road, 2-Way Lights

Start Date: 19th September 2025

End Date: 21st October 2025

 

Section 5 – Clarence Road, 2-Way Lights

Start Date: 7th October 2025

End Date: 31st October 2025

 

Section 6 – Clarence Road, 3-Way Lights 

Start Date: 22nd October 2025

End Date: 10th November 2025

Section 7 – Clarence Road, 3-Way Lights 

Start Date: 31st October 2025

End Date: 19th November 2025

 