  • Boston Towers –  Laterals and Risers – 100% mechanical complete –wiring and sprinklers to install
  • Cherry Court – Laterals and Risers – 100% mechanical complete – wiring and sprinklers to install
  • Spalding Towers –  Laterals and Risers – 100% mechanical complete – wiring and sprinklers to install
  • Roxby Close – Laterals – 100% mechanical complete – risers,sprinklers and wiring to install
  • Ferriby Towers – Laterals  – 100% mechanical complete – risers to weld, sprinklers and wiring to install
  • Grantham Towers- Laterals and Risers – 50% mechanical  complete – sprinklers and wiring to install
  • All Shakespeare buildings – Laterals  – 100% mechanical complete, risers -50% complete, sprinklers and wiring to install
  • Appleton Court – Laterals and Risers –  100% mechanical  complete – wiring and sprinklers to install
  • Appleton Close –  Laterals and Risers  – 100% mechanical complete – wiring and sprinklers to install
  • Appleton Square – Laterals  – 50% mechanical  complete –  risers,sprinklers and wiring to install.
  • Saville Green – Laterals – 100%  mechanical complete – risers,sprinklers or wiring to install
  • Beckett Street – All works outstanding
  • Cromwell Heights- All works outstanding
  • Granville Road – All works outstanding
  • Lincoln Towers – All works outstanding
  • Lindsey Mount – All works outstanding
  • Marston Mount – All works outstanding
  • Torre Gardens – All works outstanding