LATEST UPDATES

Property Changeovers – Marston Mount

Changeovers are now taking place at Marston Mount, from the 11th June 2019 Residents have been informed of the works ahead of the changeovers taking place and there are laminated signs on each floor which state which floors are being worked on, that are updated each day. For any queries or questions relating to these …

Read more

Property Changeovers – Cherry Court

Changeovers are now taking place at Cherry Court, between 7th to 24th May 2019. Residents have been informed of the works ahead of the changeovers taking place and there are laminated signs on each floor which state which floors are being worked on, that are updated each day. For any queries or questions relating to …

Read more

Update on Road Disruption

As the Leeds PIPES network continues to progress, the vast majority of the district heating pipe installation is now complete. As a result, there is currently no traffic management in place on roads in relation to the Leeds PIPES network.

Property Changeovers

Changeovers within the properties connecting to the new heat and hot water system are now underway. This will see the inefficient electric heaters be replaced with a Heat Interface Unit (HIU), new pipework, radiators, thermostat controller and a vPro2 smart meter. Tenants have been given information about the changeover works and will be advised in …

Read more

Update on Road Disruption

As the Leeds PIPES network continues to progress, the vast majority of the district heating pipe installation is now complete. As a result, there is currently no traffic management in place in relation to the Leeds PIPES network.

Cross Green Energy Centre Progress

We are delighted to announce that the external structure at Cross Green has now been completely finished within the predicted timescale. All the major pieces of equipment have been delivered and are in the energy centre and Veolia have started the fit out of the steam room where the pipes will connect to the energy …

Read more

Multi Storey Flats- Progress update

Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete Roxby Close – Laterals  and Risers – 100% mechanical …

Read more

The Chimney Arrives at Saxton Gardens

We’re pleased to report that the progress continues on the Leeds PIPES project and the striking, orange chimney has arrived and been installed at the Saxton Gardens energy centre site. The chimney is 20m high, 2.9m in diameter and comprises 5 internal flues which are surrounded by an outer casing known as the windshield.  The …

Read more