LATEST UPDATES

Update on Road Disruption

As the Leeds PIPES network continues to progress, the vast majority of the district heating pipe installation is now complete. As a result, there is currently no traffic management in place on roads in relation to the Leeds PIPES network.

Property Changeovers

Changeovers within the properties connecting to the new heat and hot water system are now underway. This will see the inefficient electric heaters be replaced with a Heat Interface Unit (HIU), new pipework, radiators, thermostat controller and a vPro2 smart meter. Tenants have been given information about the changeover works and will be advised in …

Read moreProperty Changeovers

Update on Road Disruption

As the Leeds PIPES network continues to progress, the vast majority of the district heating pipe installation is now complete. As a result, there is currently no traffic management in place in relation to the Leeds PIPES network.

Multi Storey Flats- Progress update

Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete Roxby Close – Laterals  and Risers – 100% mechanical …

Read moreMulti Storey Flats- Progress update

Multi Storey Flats- Progress update

Boston Towers –  Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Cherry Court – Laterals and Risers – 100% mechanical/electrical 100% complete – Sprinklers – 100% complete Spalding Towers –  Laterals and Risers – 100% mechanical /electrical complete – Sprinklers 100% complete Roxby Close – Laterals  and Risers – 100% mechanical …

Read moreMulti Storey Flats- Progress update